In November, 421 Indian infrastructure projects, each exceeding Rs 150 crore, encountered cost overruns surpassing Rs 4.40 lakh crore, according to the Ministry of Statistics and Programme Implementation (MoSPI). Among 1,831 projects monitored by MoSPI, 421 reported cost overruns, and 845 experienced delays.
The original cost of these projects was Rs 25,10,577.59 crore. With an anticipated completion cost of Rs 29,50,997.33 crore, the overall cost overrun is of Rs 4,40,419.74 crore, which is almost 17.54% of the initial cost. As of November 2023, Rs 15,58,038.07 crore had been spent, representing 52.80% of the projects' expected costs.
When recalculated based on the latest schedule of completion, the number of delayed projects decreases to 629. Within the delayed projects, 204 face delays of 1-12 months, 198 are delayed for 13-24 months, 322 projects experience delays of 25-60 months, and 121 projects are delayed by more than 60 months. The average time overrun for these 845 delayed projects is reported at 36.64 months.
Project implementing agencies highlighted delays in land acquisition, obtaining forest and environment clearances, and insufficient infrastructure support as the major reason for delays. Other contributing factors include delays in securing project financing, finalizing detailed engineering, alterations in project scope, issues in the tendering process, delays in equipment supply, and law and order problems. The state-wise lockdowns due to COVID-19 in 2020 and 2021 was also a notable factor causing delays in project implementation.
This comprehensive analysis paints a vivid picture of the challenges plaguing large-scale infrastructure projects in India, encompassing financial, logistical, and regulatory hurdles. Despite a recalibration of delayed projects, challenges persist. These findings emphasize the need for comprehensive reforms and effective project management strategies in the Indian infrastructure landscape for sustained economic development.
Propscience is India’s dedicated property news portal. We cover the latest events, news, trends, deals, new launches and more.
All our services and tools are completely free of cost and available 24X7!
We use cookies to give you the best possible service while using our website, please click accept and carry on browsing if you're happy with this. For more information see our Privacy Policy.
Okay, Got it!This disclaimer ("Disclaimer") is applicable to the entire Site. Upon entering the Site it is recommended that you immediately read the Terms and Conditions and Privacy Policy listed therein. Your continued usage of this Site will indicate your unconditional acceptance of the said Terms and Conditions and Privacy Policy. You hereby agree that Propscience reserves the right to modify at any time, the Terms and Conditions and Privacy Policy governing this Site without prior notification. Your usage of the Site implies that you will be bound by any such modification. You agree and acknowledge that it is your responsibility to periodically visit the Site and stay updated with the Terms and Conditions and Privacy Policy of the Website.
The information contained in this Site has been provided by Propscience for information purposes only. This information does not constitute legal, professional or commercial advice. Communication, content and material within the Site may include photographs and conceptual representations of projects under development. All computer-generated images shown on the Site are only indicative of actual designs and are sourced from third party sites.
The information on this Site may contain certain technical inaccuracies and typographical errors. Any errors or omissions brought to the attention of Propscience will be corrected as soon as possible. The content of this Site is being constantly modified to meet the terms, stipulations and recommendations of the Real Estate Regulation Act, 2016 ("RERA") and rules made thereunder and may vary from the content available as of date. All content may be updated from time to time and may at times be out of date. Propscience accepts no responsibility for keeping the information in this website up to date or any liability whatsoever for any failure to do so.
While every care has been taken to ensure that the content is useful, reliable and accurate, all content and information on the Site is provided on an "as is" and "as available" basis. Propscience does not accept any responsibility or liability with regard to the content, accuracy, legality and reliability of the information provided herein, or, for any loss or damage caused arising directly or indirectly in connection with reliance on the use of such information. No information given under this Site creates a warranty or expands the scope of any warranty that cannot be disclaimed under applicable law.
This Site provides links to other websites owned by third parties. Any reference or mention to third party websites, projects or services is for purely informational purposes only. This information does not constitute either an endorsement or a recommendation. Propscience accepts no responsibility for the content, reliability and information provided on these third-party websites. Propscience will not be held liable for any personal information of data collected by these third parties or for any virus or destructive properties that may be present on these third-party sites.
Your use of the Site is solely at your own risk. You agree and acknowledge that you are solely responsible for any action you take based upon this content and that Propscience is not liable for the same. All details regarding a project/property provided on this Site are updated on the basis of information available from the respective developers/owners/promoters. All such information will not be construed as an advertisement. To find out more about a project / development, please register/contact us to visit the site you are interested in. All decisions taken by you in this regard will be taken independently and Propscience will not be liable for any such loss in connection with the same. This Site is for guidance only. Your use of this Site - including any suggestions set out in the Site and or any use of the resources available on this Site, do not create any professional - client relationship between you and Propscience. Propscience cannot accept you as a client until certain formalities and requirements are met.
We use cookies to give you the best possible service while using our website, please accept it and continue browsing if you're happy with this. For more information see our Privacy Policy