Project
Project Name Micl Aaradhya One Earth Phase Vi |
Locality Ghatkopar (east) |
Sub Locality -- |
Builder's Name Micl Group |
RERA Number(s) P51800029288 |
Price Range 3.84 cr to 5.36 cr |
Configuration Range 3 BHK , 4 BHK |
Construction Status Under Construction |
Project Layout | Project Layout by RERA | ||
Number of Towers | 1 | Total Building Count | 1 |
Number of Units | 62 | Sanctioned Building Court | 1 |
Type of Development | Complex | Proposed but not sanctioned buildings count | -- |
Land Parcel | 0.14 Acre | Aggregate Area (in sqmts) of recreational open space | -- |
Layout | View Layout |
Project Name Ghatkopar Avenue Aaradhya One Earth G Phase Vi |
Project Type Residential |
Project Status New Project |
Proposed Date of Completion 2025-06-30 |
Revised Proposed Date of Completion -- |
Number of Flats Sold 44 |
Built-up Area as per proposed FSI (in sqmts)(Proposed but not sanctioned) 0 |
Total FSI 7170.00 |
Total Built-up Area as per approved FSI 7170 |
Sports |
Leisure |
Business & Hospitality |
Security & Sanitation |
Green Features |
Vertical Transportation |
Amenities | Available | Percentage | Detail |
---|---|---|---|
Internal Roads & Footpaths : | No | -- | Na |
Water Conservation, Rain Water Harvesting : | Yes | -- | Yet To Start |
Energy Management : | No | -- | Na |
Fire Protection And Fire Safety Requirements : | Yes | -- | Yet To Start |
Electrical Meter Room, Sub-station, Receiving Station : | Yes | -- | Yet To Start-no Sub Station |
Aggregate Area Of Recreational Open Space : | No | -- | Na |
Open Parking : | No | -- | Na |
Water Supply : | Yes | -- | Yet To Start |
Sewerage (chamber, Lines, Septic Tank , Stp) : | Yes | -- | Yet To Start |
Storm Water Drains : | Yes | -- | Yet To Start |
Landscaping & Tree Planting : | Yes | -- | Yet To Start |
Street Lighting : | No | -- | Na |
Community Buildings : | No | -- | Na |
Treatment And Disposal Of Sewage And Sullage Water : | Yes | -- | Yet To Start |
Solid Waste Management And Disposal : | Yes | -- | Yet To Start |
Parking Name | Proposed | Booked | Work Done |
---|---|---|---|
Garages | -- | -- | -- |
Covered Parking | 110 | 73 | -- |
Parking Available
Basement or over-ground with ramp parking
Car Parking Units
110
Power Backup
Complete Power Backup