Dedicated locality research platform

1st Habitable Floor

1st Floor

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

Gated Complex

Tower Name Rustomjee Virar Avenue L1-L2 and L4 Wing G Fire Exits 1
Total Floors 14 Refuge Areas 1
Number of Elevators 2 Configurations Present 1 BHK
Flats Per Floor 8 Tower Layout View Layout
Tower Name Rustomjee Virar Avenue L1-L2 and L4 Wing G Fire Exits 1
Total Floors 14 Refuge Areas 1
Number of Elevators 2 Configurations Present 2 BHK
Flats Per Floor 8 Tower Layout View Layout
Tower Name Rustomjee Virar Avenue L1-L2 and L4 Wing G Fire Exits 1
Total Floors 14 Refuge Areas 1
Number of Elevators 2 Configurations Present 2 BHK
Flats Per Floor 8 Tower Layout View Layout
Wing Name Wing G Number of Podium 2
Number of Basements -- Number of Slabs of Superstructure 15
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 28-08-2022
Possession Availability as per RERA
Proposed Date of Completion 28-02-2023
Revised Proposed Date of Completion 28-02-2024
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure --
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --