Dedicated locality research platform

1st Habitable Floor

1st

Views
--
Floor to Ceiling Height

--

Project Theme

Gated Community

Tower Name A-Wing Fire Exits 2
Total Floors 13 Refuge Areas 1
Number of Elevators 2 Configurations Present 1 BHK,2 BHK,3 BHK
Flats Per Floor 5 Tower Layout
Tower Name B-Wing Fire Exits 2
Total Floors 13 Refuge Areas 1
Number of Elevators 2 Configurations Present 1 BHK,2 BHK,3 BHK
Flats Per Floor 5 Tower Layout
Wing Name A WING , B WING Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 13
Number of Plinth 1 Number of Stilts 1
Wing Name PARMAR BUILDING NO 2 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 4
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date 31-07-2020
Possession Availability as per RERA
Proposed Date of Completion 31-07-2018
Revised Proposed Date of Completion 01-08-2019
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 93
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 76
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 50
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 83
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 60
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 30
View More
View Less
Amenities
© Propscience.com. All Rights Reserved.