Dedicated locality research platform

1st Habitable Floor

5th Floor

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

NA

Tower Name Tower 1 Fire Exits 2
Total Floors 41 Refuge Areas 2
Number of Elevators 3 Configurations Present 2 BHK,3 BHK
Flats Per Floor 6 Tower Layout
Tower Name Tower 2 Fire Exits 2
Total Floors 41 Refuge Areas 2
Number of Elevators 3 Configurations Present 2 BHK,3 BHK
Flats Per Floor 6 Tower Layout
Tower Name Tower 3 Fire Exits 2
Total Floors 41 Refuge Areas 2
Number of Elevators 3 Configurations Present 2 BHK,3 BHK
Flats Per Floor 6 Tower Layout
Wing Name Tower 1 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 40
Number of Plinth 1 Number of Stilts --
Wing Name Tower 3 Number of Podium 7
Number of Basements 5 Number of Slabs of Superstructure 42
Number of Plinth 1 Number of Stilts --
Wing Name Tower 2 Number of Podium 7
Number of Basements 4 Number of Slabs of Superstructure 42
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date 30-10-2025
Possession Availability as per RERA
Proposed Date of Completion 30-04-2026
Revised Proposed Date of Completion 30-09-2026
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth --
1 X Number Of Podiums 50
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure --
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate --