1st Habitable Floor

11th floor

Views
Water Body / City Skyline
Floor to Ceiling Height

Greater than 10 feet

Project Theme

Arabian Sea, Siddhivinayak Temple View

Tower Name South Fire Exits 2
Total Floors 47 Refuge Areas 3
Number of Elevators 8 Configurations Present 3 BHK,4 BHK,4.5 BHK
Flats Per Floor 4 Tower Layout View Layout
Tower Name North Fire Exits 2
Total Floors 47 Refuge Areas 3
Number of Elevators 8 Configurations Present 3 BHK,4 BHK,4.5 BHK
Flats Per Floor 3 Tower Layout View Layout
Wing Name 25 South 11th To 47th Floors Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 40
Number of Plinth -- Number of Stilts 1
Possession Availability
Possession Date 31-12-2025
Possession Availability as per RERA
Proposed Date of Completion 31-12-2020
Revised Proposed Date of Completion 30-06-2026
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 100
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 75
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 10
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 18
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate --