09 Feb 23

Slab Work Is Completed. Internal Work In Progress.

10 Mar 22

All the RCC work is completed. Internal finish work is almost complete. Currently painting work is going on. The builder is planning to give possession by June-July,2022

01 Jul 20

11th slab done. 12th slab casting WIP. For A wing- 1st slab work to start.

24 Jan 20

Wing A- Plinth Complete, Wing B,C,D- Eighth slab complete.

Write a review for this project

No Data found

WE ARE HERE TO HELP YOU!

WHY DOWNLOAD A PROP-REPORT?

  • An executive summary of the project.
  • Prepared in an easy to read format.
  • Download and print as and when required.
  • Provides you with all the information and details of the project.
  • Helps you to make an informed and intelligent purchase decision.
  • Once you downloaded it feel proud to be a privileged member of Propscience.com.
Comming Soon
Comming Soon
© Propscience.com. All Rights Reserved.