Project
Project Name Raunak Centrum |
Locality Chembur (east) |
Sub Locality -- |
Builder's Name Raunak Group |
RERA Number(s) P51800006705 |
Price Range 1.32 cr to 1.32 cr |
Configuration Range 1 BHK , 2 BHK , 3.5 BHK |
Construction Status Under Construction |
Project Layout | Project Layout by RERA | ||
Number of Towers | 1 | Total Building Count | 3 |
Number of Units | 221 | Sanctioned Building Court | 1 |
Type of Development | Complex | Proposed but not sanctioned buildings count | 2 |
Land Parcel | 0.32 Acre | Aggregate Area (in sqmts) of recreational open space | 749.9 |
Layout | View Layout |
Project Name Raunak Centrum |
Project Type Residential |
Project Status On-going Project |
Proposed Date of Completion 2026-12-31 |
Revised Proposed Date of Completion 2027-06-30 |
Number of Flats Sold 190 |
Built-up Area as per proposed FSI (in sqmts)(Proposed but not sanctioned) 5000 |
Total FSI 15501.00 |
Total Built-up Area as per approved FSI 10501 |
Sports |
Leisure |
Green Features |
Security & Sanitation |
Business & Hospitality |
Vertical Transportation |
Amenities | Available | Percentage | Detail |
---|---|---|---|
Internal Roads & Footpaths : | Yes | -- | No Footpath Only Internal Road |
Water Conservation, Rain Water Harvesting : | Yes | -- | Work Yet To Commence |
Energy Management : | No | -- | Na |
Fire Protection And Fire Safety Requirements : | Yes | 5 | Work In Progress |
Electrical Meter Room, Sub-station, Receiving Station : | Yes | 50 | Work In Progress |
Aggregate Area Of Recreational Open Space : | No | -- | Na |
Open Parking : | No | -- | Na |
Water Supply : | Yes | -- | Pipelines Only. Water Will Be Provided By Bmc |
Sewerage (chamber, Lines, Septic Tank , Stp) : | Yes | 50 | Work In Progress |
Storm Water Drains : | Yes | -- | Work Yet To Commence |
Landscaping & Tree Planting : | Yes | -- | Work Yet To Commence |
Street Lighting : | Yes | -- | Work Yet To Commence |
Community Buildings : | No | -- | Na |
Treatment And Disposal Of Sewage And Sullage Water : | Yes | 50 | Work In Progress |
Solid Waste Management And Disposal : | Yes | -- | Work Yet To Commence |
Parking Name | Proposed | Booked | Work Done |
---|---|---|---|
Garages | -- | -- | -- |
Covered Parking | 252 | -- | -- |
Parking Available
Basement or over-ground with ramp parking
Car Parking Units
Power Backup
Complete Power Backup