1st Habitable Floor

Ground

Views
Open Grounds / Landscape / Project Amenities
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

Small budget homes

Tower Name BLOCK NO 4 Fire Exits 3
Total Floors 4 Refuge Areas --
Number of Elevators 2 Configurations Present 1 BHK,2 BHK
Flats Per Floor 14 Tower Layout View Layout
Tower Name BLOCK NO 7 Fire Exits 2
Total Floors 4 Refuge Areas --
Number of Elevators 2 Configurations Present Studio,1 BHK
Flats Per Floor 31 Tower Layout
Tower Name BLOCK NO 9 Fire Exits 2
Total Floors 4 Refuge Areas --
Number of Elevators 2 Configurations Present 1 BHK,2 BHK
Flats Per Floor 11 Tower Layout View Layout
Wing Name BLOCK NO 4 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 5
Number of Plinth 1 Number of Stilts --
Wing Name BLOCK NO 7 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 5
Number of Plinth 1 Number of Stilts --
Wing Name BLOCK 9 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 5
Number of Plinth 1 Number of Stilts --
Possession Availability
Possession Date 31-12-2020
Possession Availability as per RERA
Proposed Date of Completion 30-12-2021
Revised Proposed Date of Completion N/A
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums --
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 100
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 100
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 100
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 100
View More
View Less
Amenities