Dedicated locality research platform

1st Habitable Floor

5th

Views
--
Floor to Ceiling Height

--

Project Theme

Exclusive Residences With No Common Walls.Separate Amenities ...

Tower Name Tower 1 Fire Exits 2
Total Floors 39 Refuge Areas 3
Number of Elevators 3 Configurations Present 2 BHK,3 BHK
Flats Per Floor 6 Tower Layout View Layout
Tower Name Tower 2 Fire Exits 2
Total Floors 39 Refuge Areas 3
Number of Elevators 3 Configurations Present 2 BHK,3 BHK
Flats Per Floor 6 Tower Layout View Layout
Wing Name Tower 1 Number of Podium 4
Number of Basements -- Number of Slabs of Superstructure 39
Number of Plinth 1 Number of Stilts 1
Wing Name Tower 2 Number of Podium 4
Number of Basements -- Number of Slabs of Superstructure 39
Number of Plinth 1 Number of Stilts 1
Wing Name Tower 3 Number of Podium 4
Number of Basements -- Number of Slabs of Superstructure 39
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 30/09/2024
Possession Availability as per RERA
Proposed Date of Completion 30-03-2025
Revised Proposed Date of Completion N/A
Sr. No Task/Activity % Work Done
1 Excavation --
1 X Number Of Basement(s) And Plinth --
1 X Number Of Podiums --
1 Stilt Floor --
1 X Number Of Slabs Of Super Structure --
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises --
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises --
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. --
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing --
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr --