Dedicated locality research platform

1st Habitable Floor

5th

Views
Road View / No View
Floor to Ceiling Height

Between 9 and 10 feet

Project Theme

Strategically constructed and located

Tower Name Gami Regan Fire Exits --
Total Floors 25 Refuge Areas --
Number of Elevators 3 Configurations Present 1 BHK,2 BHK,3 BHK
Flats Per Floor 8 Tower Layout View Layout
Wing Name 1 Number of Podium 3
Number of Basements 1 Number of Slabs of Superstructure 22
Number of Plinth 1 Number of Stilts 1
Wing Name 2 Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 6
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date 31/12/2022
Possession Availability as per RERA
Proposed Date of Completion 30-06-2023
Revised Proposed Date of Completion N/A
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 95
1 X Number Of Podiums 95
1 Stilt Floor 90
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 92
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 75
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 97
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 95
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /crz Noc, Finishing To Entrance Lobby/s, Plinth Protection, Paving Of Areas Appurtenant To Building/wing, Compound Wall And All Other Requirements As May Be Required To Obtain Occupation /completion Certificate 85
View More
View Less
Amenities
© Propscience.com. All Rights Reserved.