Dedicated locality research platform

1st Habitable Floor

3rd

Views
--
Floor to Ceiling Height

--

Project Theme

Strategically constructed and located

Tower Name Wing A Fire Exits 2
Total Floors 38 Refuge Areas --
Number of Elevators 3 Configurations Present 2 BHK,3 BHK
Flats Per Floor 2 Tower Layout View Layout
Tower Name Wing B Fire Exits 2
Total Floors 38 Refuge Areas --
Number of Elevators 3 Configurations Present 2 BHK
Flats Per Floor 2 Tower Layout View Layout
Tower Name Wing C Fire Exits 2
Total Floors 38 Refuge Areas --
Number of Elevators 3 Configurations Present 2 BHK,3 BHK
Flats Per Floor 2 Tower Layout View Layout
Tower Name Wing D Fire Exits 2
Total Floors 28 Refuge Areas --
Number of Elevators 3 Configurations Present 2 BHK
Flats Per Floor 2 Tower Layout View Layout
Wing Name Shopping Number of Podium --
Number of Basements -- Number of Slabs of Superstructure 2
Number of Plinth 1 Number of Stilts 1
Wing Name Wing A Number of Podium 3
Number of Basements -- Number of Slabs of Superstructure 37
Number of Plinth 1 Number of Stilts 1
Wing Name Wing B Number of Podium 3
Number of Basements -- Number of Slabs of Superstructure 37
Number of Plinth 1 Number of Stilts 1
Wing Name Wing C Number of Podium 3
Number of Basements -- Number of Slabs of Superstructure 37
Number of Plinth 1 Number of Stilts 1
Wing Name Wing D Number of Podium 3
Number of Basements -- Number of Slabs of Superstructure 27
Number of Plinth 1 Number of Stilts 1
Possession Availability
Possession Date
Possession Availability as per RERA
Proposed Date of Completion 31-12-2017
Revised Proposed Date of Completion 31-12-2018
Sr. No Task/Activity % Work Done
1 Excavation 100
1 X Number Of Basement(s) And Plinth 100
1 X Number Of Podiums 100
1 Stilt Floor 100
1 X Number Of Slabs Of Super Structure 100
1 Internal Walls, Internal Plaster, Floorings Within Flats/premises, Doors And Windows To Each Of The Flat/premises 100
1 Sanitary Fittings Within The Flat/premises,electrical Fittings Within The Flat/premises 100
1 Staircases, Lifts Wells And Lobbies At Each Floor Level Connecting Staircases And Lifts, Overhead And Underground Water Tanks. 100
1 The External Plumbing And External Plaster, Elevation, Completion Of Terraces With Waterproofing Of The Building/wing 100
1 Installation Of Lifts, Water Pumps, Fire Fighting Fittings And Equipment As Per Cfo Noc, Electrical Fittings To Common Areas, Electro, Mechanical Equipment, Compliance To Conditions Of Environment /cr 100